坂澜大道电力管线施工专项方案
深圳市坂澜大道道路工程Ⅱ—主线工程电力管线施工专项方案编制人:审核人:批准人:江苏省镇江市路桥工程总公司2011年3月1目录第一章总则.............................................................................................3第一节编制依据及原则.....................................................................................................3第二章工程概况.....................................................................................42.1电力主要施工内容...........................................................................................................42.2主要设备表.......................................................................................................................42.3电力管沟分段划分...........................................................................................................42.4电力管沟布置..................................................................................................................4第三章施工安排.....................................................................................53.1施工准备...........................................................................................................................53.2施工段落划分.................................................................................................................11第四章施工技术方案...........................................................................114.1测量放样.........................................................................................................................114.2施工工艺流程(见4.1-1)...........................................................................................124.3沟槽开挖........................................................................................................................124.4排管安装........................................................................................................................124.5电缆沟接地....................................................................................................................124.6砖砌电缆井.....................................................................................................................134.7电缆沟回填....................................................................................................................13第五章施工管理网络体系...................................................................135.1施工管理网络................................................................................................................135.2管理人员职责................................................................................................................14第六章质量承诺、保证体系和措施...................................................176.1质量目标........................................................................................................................176.2工程质量管理网络体系.................................................................................................176.4有关材料试验的制度....................................................................................................186.5质量保证措施................................................................................................................196.6夏、雨季施工防范措施.................................................................................................20第七章确保施工工期的措施...............................................................217.1从施工计划编制安排上保证.........................................................................................217.2从机械配备人员落实上保证.........................................................................................217.3从材料供应上保证........................................................................................................217.4从资金供应上保证........................................................................................................21第八章安全、文明生产保证措施.......................................................218.1安全生产保证措施.........................................................................................................218.2砼及钢筋砼施工安全技术措施.....................................................................................248.3文明施工保证措施........................................................................................................248.4环保工作........................................................................................................................25第九章电力施工大样图.......................................................................262第一章总则第一节编制依据及原则1.1编制依据1、依据深圳市交通公用设施建设中心发出的《深圳市坂澜大道Ⅱ标段—主线工程》的施工招标文件;2、依据深圳市市政设计研究院有限公司的《深圳市坂澜大道Ⅱ标段—主线工程》(设计号为:08072)电气工程的施工图纸内容;3、国家现行的有关市政工程建设的施工技术规范及施工规程和市政工程质量检验评定标准及验收办法,以及深圳市现行的有关工程施工技术规程和《深圳市“净畅宁工程”实施方案》、《深圳市建设工程现场文明施工管理办法》;4、结合双方签订的工程施工承包单价合同及其它有关规定等;5、本公司的施工能力,现有的机械设备、技术实力和同类工程施工实践积累的施工经验等;6、依据国家的法律、法规、法令条款,广东省及深圳市有关施工安全、人员健康、劳动保护、环境保护与文明施工方面的具体规定和技术标准;尊重和保护当地民众多年来形成的民俗风情与行为惯例
1.2编制原则1、严格遵循设计文件、技术规范和质量验收标准的原则
在编写施工组织中,严格按设计要求,认真执行国家现行的技术规范和质量验收标准,正确科学组织施工,确保工程质量达到合格标准;2、坚持实事求是的原则
在制定的施工组织方案中,充分发挥我司的技术优势和专业化、机械化联合作业的特点,坚持科学组织、合理安排、均衡生产,确保高速度、高质量、高效益地完成本市政道路工程建设
3、根据项目法施工的原则,组织本工程项目施工
通过与业主、监理和设计单位的充分合作,综合运用人员、机械、物资、资金和信息
实现质量和造价的最佳组合
实事求是的确定施工工期、施工方案,确保按期、优质、高效地完成所有的工程项目;4、积极推广应用四新成果的原则,在各项工序施工中,对于能够提高工程质量、加快施工进度、降低施工成本的新技术、新设备、新材料要积极采用,充分发挥科技在市政工程中的先导5、强化精品意识,向业主交一项优质工程,为深圳市民做出新的贡献
3第二章工程概况坂澜大道2标(K0+690~K3+700),道路南端与稼先路相接,北端与机荷高速相接,在环城北路和中浩一路之间有现状的电力,其它为新建管道
2.1电力主要施工内容1、新建2座箱式变电站,125KVA和160KVA
2、其它配套管线设计起点至坂李大道道路东侧设置1.4M×1.6M复合电缆沟,坂李大道北侧至K3+700设置12¢150电力管群,在坂李大道南侧设置2(1.4M×1.6M)复合电缆双沟,电力管群设在道路东侧人行道或设施带下,在桩号K0+736和K1+991预留6¢150电力横过管,在桩号K2+820和K3+144预留4¢150电力横过管
2.2主要设备设备名称规格型号进场数量进场日期技术状况型材切割机BORC—43551台2011.3.1良好交流发电机JF27231台2011.3.1良好电焊机BX1—4002台2011.3.1良好东风五十铃作业车SE5110GSS1部2011.3.1良好钢筋弯曲机GW402台2011.3.1良好灰浆搅拌机UJZA1台2011.3.1良好灰浆搅拌机UJZ300A1台2011.3.1良好混凝土切割机12型、18型2台2011.3.1良好小松勾机SK601台2011.3.1良好2.3电力管沟分段划分1、K0+690~134.647为新建1.4M×1.6M电缆沟2、K1+226.764~K1+916为扩建1.4M×1.6M电缆沟3、K1+916~K2+242为新建1.4M×1.6M电缆沟4、过坂李大道路口埋管16¢150长81M.5、坂李大道南侧2(1.4M×1.6M)新建电缆沟长59M6、K2+290~K2+370新建1.OM×1.0M电缆沟80M.7、K2+370~K3+700新建埋管12¢150玻璃钢管2.4电力管沟布置1、电缆沟采用覆土隐蔽式,设置在东侧人行道上,电缆沟外边设置立道牙,以防绿化带积水进入电缆沟,电缆沟转角、端头及过路管处、电缆中间接头均设置活动盖板,直线段以此为基点每隔15M设置7块活动盖板
42、电缆沟1.4M×1.6M支架采用高强度耐腐蚀的玻璃钢支架,1.0M×1.OM采用混凝土支架
3、埋管采用玻璃钢管,过机动车道采用混凝土包封,对管道埋深小于0.8M时¢150采用涂塑钢管,电力管跟电缆沟连接处设置衔接井
4、电力通道全线设置接地装置,其中复合电缆沟两侧侧壁通长敷设50×50镀锌扁钢,每回接地线间隔30米设接地极L50×50×5×2500镀锌角铁,电力管群两侧通长埋设¢16镀锌圆钢,管群两端设接地极L50×50×5×2500镀锌角钢
5、电缆沟及人孔井排水;在沟内最低处及衔接井底设置排水管,每隔一雨水井设置排水管,排水管采用塑料增强管UPVC~150按大于或等于1﹪坡度排至就近雨水井
第三章施工安排3.1施工准备1、准备工作①施工全过程做到“六落实”即施工负责人、施工员、质安员“三位一体”人员落实;施工方案、施工技术措施落实;施工机械设备、检测手段落实
对现场有关管理人员、班组长、操作人员的技术交底及施工规范、质量验收标准交底落实,各级人员的岗位职责落实,安全质量奖惩制度落实
②在开工之前,我们将查明施工区域内原有地下管线的埋设情况,并以书面报告的形式提出具体的解决办法,报请监理工程师批准后方可开工
对管道施工所经路线的障碍物进行初步清除,为以后的测量放线定位工序提供较好施工条件
2、测量放样进行施工放样测量前测量人员先校核施工图纸,按施工图纸提供的排水工程的位置和标高,定出沟槽中线及井位并引出水准基准点,作为整个排水工程的控制点
每次测量均要闭合,按规范严格控制闭5